Guidelines for Grid Connection Solar Power System
Steps to be Followed by Customer , Installer , Distribtor and Retailer
Customer - Everyone / Yourself
Installer - Thats us - Accredited BCSE Installer -J L Electrics Pty Ltd
Retailer - Your Electricity Supply Authority eg. Origin energy/ Red Energy/AGL , ETC
Distributor - Company who owns/ maintains network and distribution assets
i.e power poles,cabling,tranformers and power generating
1. System Preliminary Design -Taking into account Customer Budget - Customer /Installer
Installer to complete site analysis and design system in accordance with customers Budget and Electricity Consumption in KWH / Daily usage
In Melbourne on an average solar system produces around
1kw - 4.5kwh/day
2kw - 9kwh/day
3kw - 14kwh/day
2. Contact Electricity Retailer and negotiate Feed In Tariff Rates & Fees- Customer
3. Obtain Distributor Installation Technical Requirement and standards - Installer
4. Application for network connection of small generation power through
an approved inverter energy system with design and dawings for approval - Installer
5. Customer Rights and Obligations - Installer / Ditributor /Retailer.
6. System Installation and commissioning and Inspection - Installer / Electrical Inspector
7. Submit Electrical Works Request and copy of Certificate of Electrical safety to Retailer for Upgrading Metering to read both Import and Export Energy - Installer
8. Upgrade Metering ( Cost to be paid my Customer) - Retailer / Distributor
9. Claim government Rebate and Renewable Energy Certificate value - Installer /Customer